Metso Insights Case studies Mining and metals refining Stawell Gold improves recoveries following flotation circuit upgrade from Outotec services
Mining Metals refining
Feb 7, 2017

Stawell Gold improves recoveries following flotation circuit upgrade from Outotec services

Northgate Minerals Corporation is a leading gold and copper producer with mining operations, development projects, and exploration properties in Canada and Australia. Northgate prides itself on its strong operating abilities and has gained a reputation as one of the finest operators in the business.

Northgate’s Stawell Gold mine is located alongside the town of Stawell, northwest of Ballarat in central Victoria, Australia. Stawell has a history of gold mining dating back to the mid-19th-century Victorian gold rushes. It is an underground gold mine, with a long 26-year history, having produced its two millionth ounce in March 2010.

At Stawell, one of its main aims is to achieve operational excellence. A change in production profile requiring the processing of lower grade ore at higher throughput rates solicited the need for increased recovery condition in the milling environment.

Flotation circuit

The original flotation circuit at Stawell consisted of a bank of eight mechanical trough cells in the rougher circuit, followed by two banks of two OK3 Outotec cells as cleaners. The feed rate to the cells was between 90–105 tph, at 50–55% solids. The overall flotation circuit was not performing at an optimal rate due to entrainment problems in the rougher cells when feed density increased from 45% to 55% solids, typically at 105 tph. In anticipation of future production levels and as part of Stawell’s focus on operational excellence, it was decided to upgrade the flotation circuit at Stawell. Since site’s test work had shown that a 12.5 m3 conditioning tank was no longer required and could be removed, the new rougher cells were to be installed in that location.

Rougher circuit optimization

Following a site audit from Outotec Services, a 2 x TankCell 20 configuration was proposed to help optimize flotation operation. The old rougher circuit had all cells on the same level and was prone to back mixing, short-circuiting, and flotation inefficiency. Additionally, the old circuit had to operate with a very shallow froth depth in order to get the froth concentrate to the collection launders.

Outotec Services proposed replacing the existing rougher circuit of eight cells with two TankCell 20 cells. These cells were to be equipped with larger TankCell 30 mechanisms, which would allow operation at very high percent solids (50% and over). The TankCell design also allows a much deeper froth depth and better concentrate grade through optimized launder lip length and surface area. Outotec TankCells are renowned in the industry for their superior performance, ease of operation, and reduced power and air consumption.

Turnkey installation

Outotec Services was commissioned to handle the complete turnkey solution of the new rougher circuit, including design, supply, installation, and commissioning. This comprised all civil works, electrical, instrumentation, mechanical, ancillary equipment, piping, and structural steelwork. Plant cut-in services were also included in the project scope, along with the supply of two blowers, which were to provide for the complete flotation circuit at Stawell. The schedule was demanding but achievable, with work to commence in February 2010 and complete in September 2010, just 30 weeks later.

Partnership approach

It was decided to adopt a partnering approach between Stawell and Outotec Services, as this collaborative method ensured open communication, with all parties having greater ownership of the project and its aims. The close teamwork between Stawell and Outotec Services ensured meticulous planning and enabled the site to be fully operational at all times. Pipework and electrical easement ducts, for example, were rerouted early in the project and helped ensure continuous site operation. Issues such as tie-in points for new cells and rerouting of pipework were also planned upfront and all disruptive work was completed during shutdowns, ensuring no interruption to production. The connections to the new TankCells were conducted during one of Stawell’s scheduled shutdowns.

“The projected payback was five and a half months, so it was a pleasant surprise when it happened so soon,” explains Jodie Hendy, senior metallurgist at Stawell. “Maintenance on the TankCells has also been minimal since the upgrade. Basically we check the cells during shutdowns but there has been no maintenance required in the nine months since commissioning. The TankCells have really delivered on their reputation. Basically they do exactly what they are supposed to do.”
“The projected payback was five and a half months, so it was a pleasant surprise when it happened so soon,” explains Jodie Hendy, senior metallurgist at Stawell. “Maintenance on the TankCells has also been minimal since the upgrade. Basically we check the cells during shutdowns but there has been no maintenance required in the nine months since commissioning. The TankCells have really delivered on their reputation. Basically they do exactly what they are supposed to do.”

Challenging footprint

The planned site for the new rougher circuit was challenging and on an extremely limited footprint. The site was adjacent to a gabion wall, close to the run-of-mine pad and the reagents shed, which could not be moved. Additionally, existing process requirements before the upgrade: the old conditioning tank in a highly challenging footprint After the upgrade: Metso Outotec Services during the installation process Stawell required specific elevations for the new TankCells. Structural stability was the main issue when designing the tank support structure due to the height of the tanks and the limited footprint. Sufficient stiffness was required such that the operating frequencies of the TankCells would not interfere with the natural frequency of the tank support structure. Through FE modeling of the structure, section sizes and bracing orientations were optimized to produce the required stiffness.

Before the upgrade: the old conditioning tank in a highly challenging footprint.
Before the upgrade: the old conditioning tank in a highly challenging footprint.

Civil works

The civil work was also highly challenging. An underground slab was discovered during the excavation work of the site. In order to ascertain how to best proceed, core samples from various layers and testing were arranged by Outotec. Fortunately, it emerged that only part of the slab needed to be removed for the TankCells’ support civils. Although this caused a delay in site work, all parties worked hard to quickly resolve the issue and stay within the project timelines.

On-time commissioning

The weather proved to be an additional hurdle as the site experienced the wettest seasonal weather in recorded history during the project. Simple tasks such as curing the paintwork, which normally takes 24 hours, took days instead. Despite these challenges, the turnkey installation of the new rougher circuit, along with blowers for the complete flotation circuit, happened within deadlines. As all tie-in points had already been carefully planned upfront, commissioning was a seamless exercise.

On 13 September 2010, just 30 weeks from commencement, the new circuit, complete with TankCell technology, was commissioned and brought online – on time and within budget.

State-of-the-art flotation technology

Designed to cope with projected increases in production and considerably more operator-friendly than its predecessor, the new TankCell 20 cells have quickly proved their worth at the site. The air demand for the old rougher cells, for example, was estimated at over 3,000 Am3 /hr, whereas the estimated air demand on the TankCells is a maximum of 992 Am3 /hr.
The Metso Outotec FloatForce® rotor-stator mechanism, with its unique design, delivers enhanced flotation cell hydrodynamics and improved wear life and maintenance.

After the upgrade: Outotec Services during the installation process.
After the upgrade: Outotec Services during the installation process.

Results from site

Following the flotation upgrade at Stawell, the targeted recovery rate improvement was projected at 3.5%. The actual recovery rate, however, improved instantly by 4.5%. Payback was also impressive, occurring in less than four months.

*This case study has been written prior to the merger of Metso and Outotec.

Which modernization solution is right for you?
Obtain the potential modernization solution to benefit your flotation performance based on your flotation cell's characteristics.
Enjoyed this article? Try this next
Turn-key flotation retrofit with fast turnaround for Yamana Gold in Brazil
Outotec improved the availability and energy efficiency of the flotation cells for Yamana Gold in Brazil.
Read more
Mining Metals refining

Contact our sales to achieve similar results

Select your industry to open the form.
Mining
Metals refining
Your information is safe. Check our privacy notice for more details.
Thank you!
We will shortly contact you. You can send a new inquiry again after 15 minutes.